Phase 1
Venice/Roberston Station Funding Approved
In February, the State of California Department of Transportation approved funding for the design and construction of the Venice/Robertson aerial station and structure.
In April, the Metro Board adopted the Venice/Robertson aerial station and structure as part of the Expo Phase 1 project. The Board also increased the project budget by $54 million to a new project budget of $862.3 million.
Spring Edition of the Expo E-News is here!
Get the most up-to-date information about the Expo Light Rail Line by clicking here.
The Expo Line says good-bye to one Board Director and welcome to another.
At the May 1 Expo Board Meeting, Chair Jan Perry welcomed new member, Culver City Mayor Scott Malsin to the Expo Board of Directors. Mayor Malsin replaces former Culver City Mayor Alan Corlin as the Director representing Culver City. New Culver City councilmember Michael O'Leary has been selected as Alternate Director for Mayor Malsin.
CONSTRUCTION NEWS:
During construction of the Expo Light Rail Line it is important for safety reasons to secure the right-of-way (ROW) along Exposition Boulevard. Securing the ROW by installing K-Rail allows the contractor, FCI/Flour/Parsons (FFP), to prepare the ROW for utility relocation and improvements from Vermont Avenue to 7th Avenue. This activity begins the week of April 7. To view the full construction notice please click here.
Trench FAQ:
Wondering how long it will take to build the Trench or how many pounds of cement it will take to build it? Click here to download our Trench FAQ.
Design:
The Contractor has broken the project into
20 design packages that will be submitted for Authority and Third
Party review at the 60%, 85% and 100% design level
| |
• Design has been completed
on three work packages
• Five 85% package has
been submitted
• Eleven 60% design packages
have been received |
::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::